The Ministry of Coal has awarded the Allocation Order for the West of Tubed Coal Mine on 08th October 2025 to M/s Oriental Quarries and Mines Pvt. Ltd.  (OQMPL) for the exploration, development, operation, and commercial sale of coal, in accordance with the provisions of the Coal Block Development and Production Agreement (CBDPA) signed on 21st August 2025, and other statutory parameters prescribed by the Ministry of Coal and concerned regulatory authorities.

CLIENT:Ministry of Coal, Government of India
Project Name:West of Tubed Coal Mine
Location:Latehar District, Jharkhand
Allottee:M/s Oriental Quarries & Mines Pvt. Ltd. (OQMPL), a unit of Oriental Structural Engineers Pvt. Ltd.
Start Date:08th October 2025
Project Duration:50 Years (including a construction 5.5 years)
Current Status::Ongoing
Project Value: :To be determined post completion of detailed exploration and resource estimation
Lanes:NA

BHARAT COKING COAL LIMITED (BCCL)

Bharat Coking Coal Limited (BCCL) awarded a contract in November, 2014 for a value Rs 120.00 billion for Removal of 140.60 Lakh BCM of OB and extraction of 21.28 Lakh MT of Coal from seams at Nichitpur colliery Sijua area. Project was completed in February, 2019.
CLIENT:BCCL
START DATE OF WORK:
COMPLETION DATE OF WORK :
VALUE OF WORK:INR –
Lanes : 
STATUS :Completed

Bharat Coaking Coal Limited (BCCL)

Bharat Coaking Coal Limited (BCCL) awarded a contract in November, 2014 for a value Rs. 37.80 Billion for Removal of 250.39 Lakh BCM of OB and extraction of 70.69 Lakh MT of Coal from seams at Akashkinare colliery Govindpur area. Project was completed in December, 2020.

CLIENT:BCCL
START DATE OF WORK:
COMPLETION DATE OF WORK :
VALUE OF WORK:INR –
Lanes : 
STATUS :Completed

Mahanadi Coalfields Limited (MCL)

Mahanadi Coalfields Limited (MCL)awarded a contract in September, 2015 for a value of Rs. 35.60 Billion for extraction of coal through surface Miner at Kulda OCP of Basundhara-Garjanbahal area. Project was completed in November, 2018.

CLIENT:MCL
START DATE OF WORK:
COMPLETION DATE OF WORK :
VALUE OF WORK:INR –
Lanes : 
STATUS :Completed

Bharat Coaking Coal Limited (BCCL)

Bharat Coaking Coal Limited (BCCL) awarded a contract in November, 2015 for a value of Rs. 29.10 Billion for Removal of 224.53 Lakh BCM of OB and extraction of 77.88 Lakh MT of Coal from seams at Govindpur colliery Govindpur area. Project completion will be January, 2023.

CLIENT:BCCL
START DATE OF WORK:
COMPLETION DATE OF WORK :
VALUE OF WORK:INR –
Lanes : 
STATUS :On Going